Marriott North Ramp

    Coralville, Iowa

    Owner:

    City of Coralville

    Architect:

    Neumann Monson P.C.

    Delivery Method:

    General Contractor

    Size:

    657 Parking Spaces

    Completion Date:

    2006

    Final Cost:

    $6.3 Million

    This 600-car ramp was completed early despite an unforeseeable 5 week delay to relocate a gas pipeline, saving the City of Coralville $525K in liquidated damages. Through aggressive scheduling and re-sequencing of critical activities, Knutson made sure that the City did not incur a $15K/day penalty for late completion.